# NY20260050: Building rates for Erie County

The minimum base and fringe rates for laborers and mechanics on federally funded or assisted building construction covered by this determination in Erie County, New York.

Checked against SAM.gov on October 30, 2026.

[Check a payroll against NY20260050](https://wagepilot.ai/check-payroll?source=prevailing-wage&wd=NY20260050&county=Erie)  
[Open on SAM.gov](https://sam.gov/wage-determination/NY20260050/1)

Determination

NY20260050

Modification

1

Construction type

Building

Published

May 18, 2026

Last modified

May 18, 2026

Counties

Erie

## Rates

96 classifications, in the order the determination lists them. The rate identifier says where a rate comes from: a union agreement (such as ELEC0351-006), a union average (UAVG) or a wage survey (SU…). Letters after a fringe refer to the determination’s footnotes. The notes at the top of the determination on SAM.gov, such as federal contractor minimum wage notices and paid leave requirements, apply as well.

Classification

Rate identifier

Base

Fringe

BOILERMAKER

BOIL0007-001

$39.35

$33.18

CEMENT MASON

BRNY0045-004

$32.53

$22.10

MARBLE SETTER

BRNY0045-004

$36.85

$30.80

TILE FINISHER

BRNY0045-004

$34.71

$17.54

TERRAZZO FINISHER

BRNY0045-004

$34.71

$17.54

TILESETTER & TERRAZZO WORKER

BRNY0045-004

$38.85

$32.20

BRICKLAYER

BRNY0045-004

$39.44

$32.11

CEMENT MASON

BRNY0045-004

$32.53

$22.10

MARBLE SETTER

BRNY0045-004

$36.85

$30.80

TILE FINISHER

BRNY0045-004

$34.71

$17.54

TERRAZZO FINISHER

BRNY0045-004

$34.71

$17.54

TILESETTER & TERRAZZO WORKER

BRNY0045-004

$38.85

$32.20

BRICKLAYER

BRNY0045-004

$39.44

$32.11

CEMENT MASON

BRNY0045-004

$32.53

$22.10

MARBLE SETTER

BRNY0045-004

$36.85

$30.80

TILE FINISHER

BRNY0045-004

$34.71

$17.54

TERRAZZO FINISHER

BRNY0045-004

$34.71

$17.54

TILESETTER & TERRAZZO WORKER

BRNY0045-004

$38.85

$32.20

BRICKLAYER

BRNY0045-004

$39.44

$32.11

CEMENT MASON

BRNY0045-004

$32.53

$22.10

MARBLE SETTER

BRNY0045-004

$36.85

$30.80

TILE FINISHER

BRNY0045-004

$34.71

$17.54

TERRAZZO FINISHER

BRNY0045-004

$34.71

$17.54

TILESETTER & TERRAZZO WORKER

BRNY0045-004

$38.85

$32.20

BRICKLAYER

BRNY0045-004

$39.44

$32.11

CARPENTER

CARP0276-014

$34.73

$28.61

CABLE SPLICER

ELEC0041-003

$36.73

$23.39

ELECTRICIAN

ELEC0041-003

$44.50

$36.06

CABLE SPLICER

ELEC0041-003

$36.73

$23.39

ELECTRICIAN

ELEC0041-003

$44.50

$36.06

COMMUNICATIONS SYSTEM (SOUND WIREMAN) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK

ELEC0041-004

$44.50

$36.05

COMMUNICATIONS SYSTEM (MASTER TECHNICIAN) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK

ELEC0041-004

$44.50

$36.05

COMMUNICATIONS SYSTEM (INSTALLER) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK

ELEC0041-004

$22.90

$21.38

COMMUNICATIONS SYSTEM (CABLER) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK

ELEC0041-004

$14.20

$14.02

ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY

ELEC1249-003

$42.29

$30.66

ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY

ELEC1249-003

$52.86

$35.60

ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY

ELEC1249-003

$47.57

$31.03

ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY

ELEC1249-003

$42.29

$30.66

ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY

ELEC1249-003

$31.72

$29.87

ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)

ELEC1249-004

$49.25

$31.15

ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:)

ELEC1249-004

$49.25

$31.15

ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)

ELEC1249-004

$49.25

$31.15

ELECTRICIAN, LINE CONSTRUCTION: LINEMAN &amp;amp; TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins

ELEC1249-004

$61.56

$36.21

ELECTRICIAN, LINE CONSTRUCTION: LINEMAN &amp;amp; TECHNICIAN (Substation:)

ELEC1249-004

$61.56

$36.21

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:)

ELEC1249-004

$49.25

$31.15

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)

ELEC1249-004

$49.25

$31.15

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat

ELEC1249-004

$49.25

$31.15

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)

ELEC1249-004

$49.25

$31.15

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab

ELEC1249-004

$55.40

$31.78

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:)

ELEC1249-004

$55.40

$31.78

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)

ELEC1249-004

$55.40

$31.78

ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)

ELEC1249-004

$35.34

$30.12

ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:)

ELEC1249-004

$35.34

$30.12

ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)

ELEC1249-004

$35.34

$30.12

ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)

ELEC1249-004

$64.59

$42.92

ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:)

ELEC1249-004

$63.14

$33.82

ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY

ELEC1249-004

$49.25

$31.15

ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY

ELEC1249-004

$49.25

$31.15

ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY

ELEC1249-004

$61.56

$36.21

ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY

ELEC1249-008

$38.73

$6.93

ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY

ELEC1249-008

$20.53

$6.39

ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY

ELEC1249-008

$40.81

$6.99

ELEVATOR MECHANIC FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY

ELEV0014-001

$62.39

$38.44

POWER EQUIPMENT OPERATORS: GROUP 8 MASTER MEACHANIC NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

ENGI0017-001

$45.47

$35.40

POWER EQUIPMENT OPERATORS: GROUP 7 ANY TOWER CRANES NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

ENGI0017-001

$49.98

$35.40

POWER EQUIPMENT OPERATORS: GROUP 6 ANY CRANE 400 TONS AND OVER NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

ENGI0017-001

$49.48

$35.40

POWER EQUIPMENT OPERATORS: GROUP 5 ANY CRANE 200 - 399 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

ENGI0017-001

$48.98

$35.40

POWER EQUIPMENT OPERATORS: GROUP 4 ANY CRANE 61 - 199 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

ENGI0017-001

$48.48

$35.40

POWER EQUIPMENT OPERATORS: GROUP 3 ANY CRANE UP TO 60 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

ENGI0017-001

$47.48

$35.40

POWER EQUIPMENT OPERATORS: GROUP 2 AGGREGATE BIN, CMI AND SIMILAR TYPE CONCRETE SPREADS, CEMENT BIN, CHIPPING MACHINE AND CHIP SPREADER, COMPRESSORS (4 OR LESS), COMPRESSORS: (ANY SIZE, BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS, DUST COLLECTORS, GENERATORS, MECHANICAL HEATERS, PUMPS, WELDING MACHINES (FOUR OF ANY TYPE OR COMBINATION), CONCRETE MIXER (1/2 CU. YD. AND UNDER), FIREMAN, FORM TAMPER, FUEL TRUCK, HEATING BOILER (USED FOR TEMPRORY HEAT), JEEP TRENCHER, POWER HEATERMAN, POWER PLANT IN EXCESS OF 10 K.W., PUMP (4"" OR OVER), REVINIUS WIDENER, STEM CLEANER, STUMP CHIPPING MACHINE, WELDING MACHINE (1 MACHINE OVER 300 AMPS OR 2 OR 3 MACHINES REGARDLESS OF AMPS). NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

ENGI0017-001

$39.14

$35.40

POWER EQUIPMENT OPERATORS: GROUP 1 AIR HOIST, ALL BOOM TYPE EQUIPMENT (100 FT. OR LESS), ALL PAN AND CARRY-ALLS, ARCHER HOIST, ASPHALT ROLLER ASPHALT SPREADER OR PAVER, AUTOMATIC FINE GRADE MACHINE (CMI AND SIMILAR TYPE), ARCHER HOIST, BACKHOE AND PULL HOE (TRACTOR MOUNTED AND RUBBER MOUNTED), BACK FILLING MACHINE, BELT PLACE (CMI AND SIMILAR), BENDING MACHINE (PIPE), BITUMINOUS SPREADER AND MIXER, BLACK TOP PLANT (AUTOMATED), BLACK TOP PLANT (NON-AUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACK MOUNTED), BLOWER FOR BURNING BRUSH, BOILER (WHEN USED FOR POWER), BOOM TRUCKS, BORING MACHINE, BULLDOZER, CABLEWAY CAGE HOIST, CAISSON AUGER, CENTRAL MIX PLANT (AND ALL CONCRETE BATCHING PLANTS), CHERRY PICKER (OVER 5 TONS), CHERRY PICKER (UNDER 5 TONS), CHIPPING MACHINE AND CHIP SPREADER, CONCRETE CURB AND GUTTER MACHINES, CONCRETE CURING MACHINE, CONCRETE MIXER (OVER 1/2 CU. YD.) CONCRETE PAVEMENT SPREADERS AND FINISHERS, CONCRETE PAVER, CONCRETE PUMP, CONCRETE SAW (SELF-PROPELLED), CONVEYOR, CORE DRILL, CRANE, CRUSHER, DERRICK OPERATOR, DRAGLINE, DREDGE, DRILL RIG (TRACTOR MOUNTED), DUAL DRUM PAVER, ELECTRIC PUMP USED IN CONJUNCTION WITH WELL POINT SYSTEMS, ELEVATING GRADER SELF- PROPELLED OR TOWED), ELEVATOR EXCAVATOR (ALL PURPOSE, HYDRAULCALLY OPERATED) FARM TRACTOR WITH ACCESSORIES, FINE GRADE MACHINE, FORKLIFT, FRONT END LOADER, GENERATOR (10 OUTLETS OR MORE), GRADALL, GRADER, GROUT OR GUNITE MACHINE, HEAD TOWER, HOIST-ONE DRUM, HOISTING ENGINE, HYDRAULIC BOOM, HYDRAULIC HAMMER, (SELF PROPELLED), HYDRAULIC PIPE JACK MACHINE (OR SIMILAR TYPE MACHINE), HYDRAULIC SYSTEM PUMPS, HYDRO CRANE, HYDRO HAMMER (OR SIMILAR TYPE), INDUSTRIAL TRACTOR, JERSEY SPREADER, KOLMAN PLANT LOADER (AND SIMILAR TYPE LOADERS), LOCOMOTIVE, LUBRICATION TRUCK, MAINTENANCE ENGINEER, MAINTENANCE LUBRICATION UNIT OR TRUCK, MINE HOIST, MIXR FOR STABILIZED BASE (SELF-PROPELLED), MONORAIL, MOTORIZED HYDRAULIC PIN PULLER, MOTORIZED HYDRAULIC SEEDER MUCKING MACHINE, MULCHING MACHINE, MULTIPLE DRUM HOIST

ENGI0017-001

$44.23

$35.40

IRONWORKER: SHEETER

IRON0006-015

$35.49

$32.30

IRONWORKER

IRON0006-015

$35.49

$32.30

LABORERS: GROUP 6 HAZARDOUS WASTE WORKER

LABO0210-001

$32.43

$28.25

LABORERS: GROUP 5 ASBESTOS REMOVAL, DELEADER

LABO0210-001

$31.93

$28.25

LABORERS: GROUP 4 STONE CUTTER, CURB SETTER AND FLAG LAYER

LABO0210-001

$31.18

$28.25

LABORERS: GROUP 3 WORKER ON ANY SWING SCAFFOLD, BLASTER, PLUMBING LABORER, WAGON DRILLER, BOTTOM (CAISSON OR COFFERDAM), LASER SETTER, ASPHALT RAKERS, ASPHALT SCREED MAN

LABO0210-001

$30.71

$28.25

LABORERS: GROUP 2 MORTAR MIXER, ASPHALT SMOOTHERS, PNEUMATIC GAS ELECTRIC TOOL OPERATOR INCLUDING ALL FORMS OF BUSTERS, JACKHAMMERS, AND CHIPPING GUNS OVER 8' IN DEPTH

LABO0210-001

$30.60

$28.25

LABORERS: GROUP 1 BASIC, BOAT SAFETY MAN, FLAGMAN, TOOL ROOM MAN, NURSERYMAN DEMOLITION WORKER; TOP MAN; WRECKER; IBC BARRIERS EXCEPT ON STRUCTURERS; GUARD RAIL. ASPHALT SHOVELERS, FOUNDATION LABORERS OVER 8' IN DEPTH, HOD CARRIERS, PLASTER TENDER, PLASTER SCAFFOLD BUILDER, PNEUMATIC GAS, ELECTRIC OPERATOR, INCLUDING ALL FORMS OF BUSTERS, JACKHAMMERS, CHIPPING GUNS AND STEEL BURNERS

LABO0210-001

$30.43

$28.25

GLAZIER

PAIN0004-007

$34.68

$27.64

PAINTERS: TAPERS ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

PAIN0004-018

$26.45

$23.69

PAINTERS: SPRAYING, PAPERHANGERS, SAND BLASTING, SWINGING SCAFFOLD ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

PAIN0004-018

$25.95

$23.69

PAINTERS: LEAD ABATEMENT ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

PAIN0004-018

$25.95

$23.69

PAINTERS ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

PAIN0004-018

$25.95

$23.69

PAINTERS: TAPING/DRYWALL (ENTIRE COUNTY, (EXCLUDING AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

PAIN0004-024

$34.00

$28.51

PAINTERS: SPRAY, SANDBLASTING, SWING SCAFFOLD OR ANY HANGED RIGGING PLATFORM, EPOXY (ENTIRE COUNTY, (EXCLUDING AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

PAIN0004-024

$33.00

$28.21

PAINTERS: BRUSH & ROLL (ENTIRE COUNTY, (EXCLUDING AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

PAIN0004-024

$33.00

$28.21

PLASTERER

PLAS0009-001

$33.05

$25.09

CEMENT FINISHER

PLAS0111-001

$33.65

$31.47

PIPEFITTER: (ZONE 1) ERIE- ALL TOWNSHIPS IN THE COUNTY

PLUM0022-008

$42.20

$29.80

ROOFERS: SLATE & TILE (ERIE COUNTY)

ROOF0074-001

$35.11

$26.03

ROOFERS: COMPOSITION (ERIE COUNTY)

ROOF0074-001

$34.96

$26.03

SHEET METAL WORKER (ERIE COUNTY)

SHEE0071-001

$39.50

$29.18

SPRINKLER FITTER

SUNY1999-001

$15.94

$3.88

TRUCK DRIVERS: INCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS (ERIE COUNTY) WORK ON A HAZARDOUS WASTE SITE THEN ADDITIONAL $2.00 PER HOUR. EUCLIDS ADD $0.25 TO JOURNEYMAN RATE FOOTNOTE: A. HEALTH AND WELFARE $438.61 PER WEEK B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND AFTER THE HOLIDAY

TEAM0449-004

$47.18

$15.09

TRUCK DRIVERS:: DUMP TRUCK ONLY, EXCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND AFTER THE HOLIDAY

TEAM0449-007

$32.00

$0.00

## Other determinations for these counties

- [Erie County  
    4 determinations](https://wagepilot.ai/prevailing-wage/new-york/erie-county)

## Change history

Changes WagePilot has seen on SAM.gov since it began mirroring this determination.

- October 29, 2026  
    First seen, Modification 1.

Check your payroll against this determination

## Upload one week of payroll. The NY20260050 rates are already loaded.

[Check a payroll free](https://wagepilot.ai/check-payroll?source=prevailing-wage&wd=NY20260050&county=Erie)

**About these rates**  
WagePilot mirrors Davis-Bacon general wage determinations from SAM.gov, the official source, and re-checks each one daily. The wage determination incorporated in your contract governs, including its modification number, footnotes and any conformed classifications. WagePilot reviews payroll; it does not file, certify or give legal advice.

---

Source: https://wagepilot.ai/prevailing-wage/new-york/ny20260050 (last updated 2026-05-18)