New Jersey Davis-Bacon wage determination

NJ20260033: Building rates for Hudson County

The minimum base and fringe rates for laborers and mechanics on federally funded or assisted building construction covered by this determination in Hudson County, New Jersey.

Checked against SAM.gov on .

Determination
NJ20260033
Modification
1
Construction type
Building
Published
May 18, 2026
Last modified
May 18, 2026
Counties
Hudson

Rates

38 classifications, in the order the determination lists them. The rate identifier says where a rate comes from: a union agreement (such as ELEC0351-006), a union average (UAVG) or a wage survey (SU…). Letters after a fringe refer to the determination’s footnotes. The notes at the top of the determination on SAM.gov, such as federal contractor minimum wage notices and paid leave requirements, apply as well.

ClassificationRate identifierBaseFringe
ASBESTOS WORKER/HEAT & FROST INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead abatement)ASBE0032-008$51.74$46.20
BRICKLAYER (INCLUDING CAULKING, CLEANING AND Work on high stacks: 22% per hour additional.BRNJ0002-014$49.60$37.96
MASON - Work on high stacks: 22% per hour additionalBRNJ0002-016$49.60$37.96
MARBLE SETTERBRNJ0007-003$64.66$40.97
TILE SETTERBRNJ0007-022$64.90$37.28
TILE Work grouting all epoxy: $10.00 additional per dayBRNJ0007-022$50.05$33.90
CARPENTER (SCAFFOLD The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafterCARP0006-009$57.42$34.17
CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORMWORK, BATT AND BLOWN INSULATION)CARP0006-010$57.42$34.17
SOFT FLOOR LAYERCARP0029-008$57.42$34.17
Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.CARP0715-007$58.84$35.06
ELECTRICIAN (INCLUDING LOW VOLTAGE Work on line voltage of 440 or 480 volts: 10% per hour Work from trusses, scaffolds, frames, ladders and poles, 40 ft. or more above the ground or floor (does not include work from a manlift): 20% per hour Work on radio towers, transmission towers and smokestacks: 21% per hour additionalELEC0164-006$62.90$39.31
ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING) CABLE Work on line voltage of 440 or 480 volts: 10% per hour Work from trusses, scaffolds, frames, ladders and poles, 40 ft. or more above the ground or floor (does not include work from a manlift): 20% per hour Work on radio towers, transmission towers and smokestacks: 21% per hour additionalELEC0164-006$73.59$45.99
POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAYENGI0825-020$52.88$37.50
POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAYENGI0825-020$56.59$37.50
POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR; HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAYENGI0825-020$58.22$37.50
POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAYENGI0825-020$60.13$37.50
POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE); TRENCHER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAYENGI0825-020$61.72$37.50
IRONWORKER: STRUCTURAL AND ORNAMENTALIRON0011-012$52.24$50.32
IRONWORKER: REINFORCINGIRON0011-012$49.94$50.32
ASBESTOS REMOVAL LABORER The removal, abatement, enclosure and decontamination of personal protective equipment, chemical protective clothing and machinery relating to asbestos and/or toxic and hazardous waste or materials which shall include but not necessarily be limited to: the erection, moving, servicing and dismantling of all enclosures, scaffolding and barricades; the operation of all tools and equipment normally used in the removal or abatement of asbestos and toxic or hazardous waste or materials; the labeling, bagging, cartoning, crating, or other packaging of materials for disposal; the clean-up of the worksite; and all other work incidental to the removal, abatement, encapsulation, enclosure, and decontamination of asbestos and toxic or hazardous waste or materials; and, in addition, all work tasks involved in the maintenance and operation of energy resource recovery plants (co-generation plants)LABO0008-001$28.37$21.62
LABORER: BRICK/CEMENT/CONCRETELABO0077-002$36.50$30.22
LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, COMMON OR GENERAL LABORER, LANDSCAPE LABORER, POWER TOOL OPERATOR AND SCREEDMANLABO0077-006$35.75$30.22
DRYWALL FINISHER/TAPERPAIN0711-018$44.87$30.15
PAINTER (BRUSH & ROLLER)PAIN0711-019$45.55$29.86
PAINTER (SPRAY)PAIN0711-019$45.55$29.86
Work welding or using a cutting torch: $1.00 per hour additional. Work on a swing stage scaffold; on a pipe scaffold providing the working height of the platform is 30 ft. or above; and on motorized lifts provided that the height of the lift platform is above the second floor or above thirty feet: $1.00 per hour additionalPAIN0711-021$52.68$31.29
CEMENT MASON/CONCRETE FINISHERPLAS0029-002$54.64$30.95
PLASTERERPLAS0029-003$54.64$30.95
PLUMBER (EXCLUDING HVAC PIPE INSTALLATION)PLUM0024-001$62.09$45.05
PIPEFITTER (INCLUDING HVAC PIPE INSTALLATION) (HUDSON COUNTY (City of Bayonne; Borough of East Newark; Towns of Guttenberg and Harrison; Cities of Hoboken and Jersey City; Town of Kearney; Township of North Bergen; Town of Secaucus; City of Union City; Township of Weehawken; Town of West New York))PLUM0274-001$57.97$40.22
ROOFER (INCLUDES ALL TYPES OF ROOFERS)ROOF0004-007$44.52$32.25
ROOFER (ALL TYPES) (HUDSON COUNTY (EAST OF THE HACKENSACK RIVER))ROOF0008-005$50.25$39.62
SPRINKLER FITTER (FIRE SPRINKLERS)SFNJ0696-006$67.97$39.35
SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION)SHEE0025-005$51.30$51.55
LABORER: PIPELAYERSUNJ2004-009$38.85$0.14
ELEVATOR MECHANICSUNJ2004-009$40.21$11.22
TRUCK DRIVER: DUMP TRUCK HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour additional. Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional. Work on a state or federally designated hazardous waste site, in a zone requiring Level B, C or D personal protection for any workers other than the truck driver: $1.00 per hour PAID HOLIDAYS: New Year's Day, President's Day, Decoration Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas Day; provided that the employee has been assigned to work, or, ""shapes"", one day of the calendar week during which the holiday occursTEAM0560-002$47.36$44.02
TRUCK DRIVER: OFF THE ROAD HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour additional. Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional. Work on a state or federally designated hazardous waste site, in a zone requiring Level B, C or D personal protection for any workers other than the truck driver: $1.00 per hour PAID HOLIDAYS: New Year's Day, President's Day, Decoration Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas Day; provided that the employee has been assigned to work, or, ""shapes"", one day of the calendar week during which the holiday occursTEAM0560-002$47.51$44.02

Other determinations for these counties

Change history

Changes WagePilot has seen on SAM.gov since it began mirroring this determination.

  • First seen, Modification 1.
Check your payroll against this determination

Upload one week of payroll. The NJ20260033 rates are already loaded.

Check a payroll free

About these ratesWagePilot mirrors Davis-Bacon general wage determinations from SAM.gov, the official source, and re-checks each one daily. The wage determination incorporated in your contract governs, including its modification number, footnotes and any conformed classifications. WagePilot reviews payroll; it does not file, certify or give legal advice.