New Jersey Davis-Bacon wage determination

NJ20260061: Heavy rates for Passaic County

The minimum base and fringe rates for laborers and mechanics on federally funded or assisted heavy construction covered by this determination in Passaic County, New Jersey.

Checked against SAM.gov on .

Determination
NJ20260061
Modification
1
Construction type
Heavy
Published
May 18, 2026
Last modified
May 18, 2026
Counties
Passaic

Rates

24 classifications, in the order the determination lists them. The rate identifier says where a rate comes from: a union agreement (such as ELEC0351-006), a union average (UAVG) or a wage survey (SU…). Letters after a fringe refer to the determination’s footnotes. The notes at the top of the determination on SAM.gov, such as federal contractor minimum wage notices and paid leave requirements, apply as well.

ClassificationRate identifierBaseFringe
Work on high stacks: 22% per hour additionalBRNJ0002-018$49.60$37.96
CEMENT MASONBRNJ0004-001$49.60$37.96
CARPENTER: INCLUDING FORM WORK THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTERCARP0006-013$57.42$34.17
MILLWRIGHT Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.CARP0715-007$58.84$35.06
CARPENTER DOCK BUILDER (Concrete form Work on land pile driving, floating marine construction and the construction of wharves, while handling and working with creosote and creosote-impregnated products: $.25 per hour Work on hazardous/toxic/contaminated waste removal, on a hazardous/toxic/contaminated waste site, where the worker comes into contact with hazardous/toxic/contaminated waste material, and when A, B or C personal protective equipment is required and used for respiratory, skin or eye protection: 20% per hour additionalCARP1556-003$52.02$39.23
CARPENTER DOCK BUILDER (All other Work on land pile driving, floating marine construction and the construction of wharves, while handling and working with creosote and creosote-impregnated products: $.25 per hour Work on hazardous/toxic/contaminated waste removal, on a hazardous/toxic/contaminated waste site, where the worker comes into contact with hazardous/toxic/contaminated waste material, and when A, B or C personal protective equipment is required and used for respiratory, skin or eye protection: 20% per hour additionalCARP1556-003$52.98$52.44
ELECTRICIAN WORK FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL. WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATEELEC0102-026$65.43$42.86
ELECTRICIAN (CABLE SPLICER) WORK FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL. WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATEELEC0102-026$71.97$46.42
POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAYENGI0825-021$52.88$37.50
POWER EQUIPMENT OPERATORS: GROUP 4 BROOM; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); ROLLER, GRADE; PUMP HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAYENGI0825-021$56.59$37.50
POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER; COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); CRUSHER; FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR; HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAYENGI0825-021$58.22$37.50
POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAYENGI0825-021$60.13$37.50
POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE) HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAYENGI0825-021$61.72$37.50
IRONWORKER: STRUCTURAL AND ORNAMENTALIRON0011-012$52.24$50.32
IRONWORKER: REINFORCINGIRON0011-012$49.94$50.32
LABORER: MASON TENDER: CEMENT/CONCRETELABO0077-008$29.35$23.07
LABORER: LANDSCAPE LABORER, POWER TOOL OPERATOR HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS REQUIRED TO WEAR LEVEL A, B OR C PERSONAL PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS NOT REQUIRED TO WEAR LEVEL A, B, OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE WORKER WORKS THREE DAYS FOR THE SAME EMPLOYER WITHIN A PERIOD OF TEN WORKING DAYS CONSISTING OF FIVE WORKING DAYS BEFORE AND FIVE WORKING DAYS AFTER THE DAY UPON WHICH THE HOLIDAY FALLS OR IS OBSERVEDLABO0172-008$50.95$38.53
PAINTERS: WORK ON BRIDGES (MAJOR BRIDGES DESIGNED FOR COMMERCIAL NAVIGATION)PAIN0711-023$58.28$33.85
PAINTERS: BRUSH AND ROLLER (REPAINT WORK, ON PROJECTS ON WHICH NO MAJOR ALTERATIONS OCCUR.)PAIN0711-024$29.05$18.91
PAINTERS: BRUSH AND ROLLER (NEW CONSTRUCTION)PAIN0711-024$40.19$22.72
LABORER: PIPELAYERSUNJ2004-037$24.05$13.67
LABORER: COMMON OR GENERALSUNJ2004-037$28.65$8.52
TRUCK DRIVER: OFF THE ROAD TRUCK; PICKUP TRUCK HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL B, C OR D PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $1.00 PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE EMPLOYEE HAS BEEN ASSIGNED TO WORK, OR, ""SHAPES"", ONE DAY OF THE CALENDAR WEEK DURING WHICH THE HOLIDAY OCCURSTEAM0560-003$47.51$44.02
TRUCK DRIVER: DUMP TRUCK; FLATBED TRUCK HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL B, C OR D PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $1.00 PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE EMPLOYEE HAS BEEN ASSIGNED TO WORK, OR, ""SHAPES"", ONE DAY OF THE CALENDAR WEEK DURING WHICH THE HOLIDAY OCCURSTEAM0560-003$47.36$44.02

Other determinations for these counties

Change history

Changes WagePilot has seen on SAM.gov since it began mirroring this determination.

  • First seen, Modification 1.
Check your payroll against this determination

Upload one week of payroll. The NJ20260061 rates are already loaded.

Check a payroll free

About these ratesWagePilot mirrors Davis-Bacon general wage determinations from SAM.gov, the official source, and re-checks each one daily. The wage determination incorporated in your contract governs, including its modification number, footnotes and any conformed classifications. WagePilot reviews payroll; it does not file, certify or give legal advice.