NY20260008: Heavy, Highway rates for Cattaraugus, Chautauqua, Erie Counties
The minimum base and fringe rates for laborers and mechanics on federally funded or assisted heavy, highway construction covered by this determination in Cattaraugus, Chautauqua, Erie Counties, New York.
Checked against SAM.gov on .
- Determination
- NY20260008
- Modification
- 3
- Construction type
- Heavy, Highway
- Published
- July 30, 2026
- Last modified
- July 30, 2026
- Counties
- Cattaraugus, Chautauqua, Erie
Rates
106 classifications, in the order the determination lists them. The rate identifier says where a rate comes from: a union agreement (such as ELEC0351-006), a union average (UAVG) or a wage survey (SU…). Letters after a fringe refer to the determination’s footnotes. The notes at the top of the determination on SAM.gov, such as federal contractor minimum wage notices and paid leave requirements, apply as well.
| Classification | Rate identifier | Base | Fringe |
|---|---|---|---|
| HAZARDOUS MATERIAL HANDLER | ASBE0004-001 | $34.15 | $26.09 |
| ASBESTOS WORKER/HEAT & FROST INSULATOR (INCLUDE APPLICATION OF ALL MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS) | ASBE0004-001 | $37.65 | $30.69 |
| BOILERMAKER | BOIL0007-001 | $39.35 | $33.18 |
| CEMENT MASON/CONCRETE FINISHER (CHATAUQUA COUNTY AND CATTARAUGUS COUNTY (EXCLUDING TWNSP OF PERRYSBURG)) | BRNY0008-004 | $38.63 | $25.05 |
| TILESETTER & TERRAZZO WORKER (ERIE, CATTARAUGUS (TOWNS OF PERRYSBURG & GOWANDA)) | BRNY0045-001 | $31.21 | $20.54 |
| MARBLE SETTER (ERIE, CATTARAUGUS (TOWNS OF PERRYSBURG & GOWANDA)) | BRNY0045-001 | $31.72 | $29.18 |
| CEMENT MASON (ERIE, CATTARAUGUS (TOWNS OF PERRYSBURG & GOWANDA)) | BRNY0045-001 | $36.82 | $31.33 |
| BRICKLAYER, STONEMASON (ERIE, CATTARAUGUS (TOWNS OF PERRYSBURG & GOWANDA)) | BRNY0045-001 | $37.44 | $32.71 |
| TERRAZZO FINISHER (ERIE, CATTARAUGUS (TOWNS OF PERRYSBURG & GOWANDA)) | BRNY0045-001 | $34.71 | $17.54 |
| TILE FINISHER (ERIE, CATTARAUGUS (TOWNS OF PERRYSBURG & GOWANDA)) | BRNY0045-001 | $34.71 | $17.54 |
| CARPENTERS: (CHAUTAUQUA; CATTARAUGUS (REMAINDER OF COUNTY) FOOTNOTES: A. PAID HOLIDAYS: INDEPENDENCE DAY AND LABOR DAY, PROVIDED THE EMPLOYEE WORKS HIS SCHEDULED DAY BEFORE AND AFTER THE HOLIDAY AND IS ON THE PAYROLL WEEK IN WHICH THE HOLIDAY FALLS | CARP0276-002 | $38.18 | $26.11 |
| CARPENTER, HEAVY & HIGHWAY (ERIE (GRAND ISLAND)) FOOTNOTES: A. PAID HOLIDAYS: INDEPENDENCE DAY, LABOR DAY, PROVIDED THE EMPLOYEE WORKS HIS SCHEDULED DAY BEFORE AND AFTER THE HOLIDAY AND IS ON THE PAYROLL IN THE PAYROLL WEEK IN WHICH THE HOLIDAY FALLS | CARP0276-013 | $41.19 | $31.55 |
| CARPENTER, HEAVY & HIGHWAY (CATTARAUGUS (TOWNSHIPS OF PERSIA AND PERRYSBURG)) FOOTNOTES: A. PAID HOLIDAYS: INDEPENDENCE DAY, LABOR DAY, PROVIDED THE EMPLOYEE WORKS HIS SCHEDULED DAY BEFORE AND AFTER THE HOLIDAY AND IS ON THE PAYROLL IN THE PAYROLL WEEK IN WHICH THE HOLIDAY FALLS | CARP0276-021 | $38.18 | $26.11 |
| CABLE SPLICER (ERIE, CATTARAUGUS (ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE, FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MANSFIELD, NEW ALBION, OTTO, PERRYSBURG, PERSIA AND YORKSHIRE TOWNSHIPS)) | ELEC0041-007 | $36.73 | $23.39 |
| ELECTRICIAN (ERIE, CATTARAUGUS (ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE, FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MANSFIELD, NEW ALBION, OTTO, PERRYSBURG, PERSIA AND YORKSHIRE TOWNSHIPS)) | ELEC0041-007 | $44.50 | $36.06 |
| COMMUNICATIONS SYSTEM (ERIE, CATTARAUGUS (ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE, FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE TOWNSHIPS)) | ELEC0041-008 | $14.20 | $14.02 |
| COMMUNICATIONS SYSTEM, INSTALLER (ERIE, CATTARAUGUS (ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE, FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE TOWNSHIPS)) | ELEC0041-008 | $22.90 | $21.38 |
| COMMUNICATIONS SYSTEM, MASTER TECHNICIAN (ERIE, CATTARAUGUS (ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE, FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE TOWNSHIPS)) | ELEC0041-008 | $44.50 | $36.05 |
| COMMUNICATIONS SYSTEM, SOUND WIREMAN (ERIE, CATTARAUGUS (ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE, FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE TOWNSHIPS)) | ELEC0041-008 | $44.50 | $36.05 |
| CABLE SPLICER (CHAUTAUQUA, CATTARAUGUS (REMAINDER OF COUNTY)) | ELEC0106-002 | $35.75 | $20.68 |
| ELECTRICIAN (CHAUTAUQUA, CATTARAUGUS (REMAINDER OF COUNTY)) | ELEC0106-002 | $42.50 | $27.23 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | ELEC1249-003 | $31.72 | $29.87 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | ELEC1249-003 | $42.29 | $30.66 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | ELEC1249-003 | $47.57 | $31.03 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | ELEC1249-003 | $52.86 | $35.60 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | ELEC1249-003 | $42.29 | $30.66 |
| ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | ELEC1249-004 | $61.56 | $36.21 |
| ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | ELEC1249-004 | $49.25 | $31.15 |
| ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | ELEC1249-004 | $49.25 | $31.15 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) | ELEC1249-004 | $63.14 | $33.82 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | ELEC1249-004 | $64.59 | $42.92 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | ELEC1249-004 | $35.34 | $30.12 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) | ELEC1249-004 | $35.34 | $30.12 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | ELEC1249-004 | $35.34 | $30.12 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | ELEC1249-004 | $55.40 | $31.78 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | ELEC1249-004 | $55.40 | $31.78 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | ELEC1249-004 | $55.40 | $31.78 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | ELEC1249-004 | $49.25 | $31.15 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | ELEC1249-004 | $49.25 | $31.15 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | ELEC1249-004 | $49.25 | $31.15 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | ELEC1249-004 | $49.25 | $31.15 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) | ELEC1249-004 | $61.56 | $36.21 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | ELEC1249-004 | $61.56 | $36.21 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | ELEC1249-004 | $49.25 | $31.15 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) | ELEC1249-004 | $49.25 | $31.15 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | ELEC1249-004 | $49.25 | $31.15 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | ELEC1249-008 | $40.81 | $6.99 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | ELEC1249-008 | $20.53 | $6.39 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | ELEC1249-008 | $38.73 | $6.93 |
| ELEVATOR MECHANIC FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY | ELEV0014-001 | $62.39 | $38.44 |
| POWER EQUIPMENT OPERATORS: GROUP 1 AIR HOIST, ALL BOOM TYPE EQUIPMENT (100 FT. OR LESS), ALL PAN AND CARRY-ALLS, ARCHER HOIST, ASPHALT ROLLER ASPHALT SPREADER OR PAVER, AUTOMATIC FINE GRADE MACHINE (CMI AND SIMILAR TYPE), ARCHER HOIST, BACKHOE AND PULL HOE (TRACTOR MOUNTED AND RUBBER MOUNTED), BACK FILLING MACHINE, BELT PLACE (CMI AND SIMILAR), BENDING MACHINE (PIPE), BITUMINOUS SPREADER AND MIXER, BLACK TOP PLANT (AUTOMATED), BLACK TOP PLANT (NON-AUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACK MOUNTED), BLOWER FOR BURNING BRUSH, BOILER (WHEN USED FOR POWER), BOOM TRUCKS, BORING MACHINE, BULLDOZER, CABLEWAY CAGE HOIST, CAISSON AUGER, CENTRAL MIX PLANT (AND ALL CONCRETE BATCHING PLANTS), CHERRY PICKER (OVER 5 TONS), CHERRY PICKER (UNDER 5 TONS), CHIPPING MACHINE AND CHIP SPREADER, CONCRETE CURB AND GUTTER MACHINES, CONCRETE CURING MACHINE, CONCRETE MIXER (OVER 1/2 CU. YD.) CONCRETE PAVEMENT SPREADERS AND FINISHERS, CONCRETE PAVER, CONCRETE PUMP, CONCRETE SAW (SELF-PROPELLED), CONVEYOR, CORE DRILL, CRANE, CRUSHER, DERRICK OPERATOR, DRAGLINE, DREDGE, DRILL RIG (TRACTOR MOUNTED), DUAL DRUM PAVER, ELECTRIC PUMP USED IN CONJUNCTION WITH WELL POINT SYSTEMS, ELEVATING GRADER SELF- PROPELLED OR TOWED), ELEVATOR EXCAVATOR (ALL PURPOSE, HYDRAULCALLY OPERATED) FARM TRACTOR WITH ACCESSORIES, FINE GRADE MACHINE, FORKLIFT, FRONT END LOADER, GENERATOR (10 OUTLETS OR MORE), GRADALL, GRADER, GROUT OR GUNITE MACHINE, HEAD TOWER, HOIST-ONE DRUM, HOISTING ENGINE, HYDRAULIC BOOM, HYDRAULIC HAMMER, (SELF PROPELLED), HYDRAULIC PIPE JACK MACHINE (OR SIMILAR TYPE MACHINE), HYDRAULIC SYSTEM PUMPS, HYDRO CRANE, HYDRO HAMMER (OR SIMILAR TYPE), INDUSTRIAL TRACTOR, JERSEY SPREADER, KOLMAN PLANT LOADER (AND SIMILAR TYPE LOADERS), LOCOMOTIVE, LUBRICATION TRUCK, MAINTENANCE ENGINEER, MAINTENANCE LUBRICATION UNIT OR TRUCK, MINE HOIST, MIXR FOR STABILIZED BASE (SELF-PROPELLED), MONORAIL, MOTORIZED HYDRAULIC PIN PULLER, MOTORIZED HYDRAULIC SEEDER MUCKING MACHINE, MULCHING MACHINE, MULTIPLE DRUM HOIST | ENGI0017-012 | $47.39 | $36.89 |
| POWER EQUIPMENT OPERATORS: GROUP 2 AGGREGATE BIN, CMI AND SIMILAR TYPE CONCRETE SPREADS, CEMENT BIN, CHIPPING MACHINE AND CHIP SPREADER, COMPRESSORS (4 OR LESS), COMPRESSORS: (ANY SIZE, BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS, DUST COLLECTORS, GENERATORS, MECHANICAL HEATERS, PUMPS, WELDING MACHINES (FOUR OF ANY TYPE OR COMBINATION), CONCRETE MIXER (1/2 CU. YD. AND UNDER), FIREMAN, FORM TAMPER, FUEL TRUCK, HEATING BOILER (USED FOR TEMPRORY HEAT), JEEP TRENCHER, POWER HEATERMAN, POWER PLANT IN EXCESS OF 10 K.W., PUMP (4"" OR OVER), REVINIUS WIDENER, STEM CLEANER, STUMP CHIPPING MACHINE, WELDING MACHINE (1 MACHINE OVER 300 AMPS OR 2 OR 3 MACHINES REGARDLESS OF AMPS). NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | ENGI0017-012 | $42.89 | $36.89 |
| POWER EQUIPMENT OPERATORS: GROUP 3 CRANES 5 - 60 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | ENGI0017-012 | $50.64 | $36.89 |
| POWER EQUIPMENT OPERATORS: GROUP 4 CRANES 61 - 199 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | ENGI0017-012 | $51.64 | $36.89 |
| POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 200 - 399 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | ENGI0017-012 | $52.14 | $36.89 |
| POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 400 TONS & OVER NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | ENGI0017-012 | $52.64 | $36.89 |
| POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | ENGI0017-012 | $48.46 | $36.89 |
| IRONWORKER (FENCE ERECTORS) | IRON0006-003 | $34.06 | $30.80 |
| IRONWORKER (STRUCTURAL, ORNAMENTAL, REINFORCING STEEL, WELDERS, RIGGERS AND RODMAN) | IRON0006-003 | $35.49 | $32.30 |
| IRONWORKER (WINDOW ERECTORS) | IRON0006-003 | $33.14 | $32.30 |
| IRONWORKER | IRON0006-015 | $35.49 | $32.30 |
| IRONWORKER: SHEETER | IRON0006-015 | $35.49 | $32.30 |
| LABORER GROUP 1 LABORERS; FLAGMEN; OUTBOARD AND HAND BOATS; DEMOLITION WORKER; IBC BARRIERS (EXCEPT ON STRUCTURES); GUARD RAILS;ROAD MARKERS (ERIE COUNTY HEAVY & HIGHWAY) FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK | LABO0210-003 | $34.66 | $28.65 |
| LABORER GROUP 2 BULL FLOAT; CHAIN SAW; CONCRETE AGGREGATE BIN; CONCRETE BOOTMAN; GIN BUGGY; HAND OR MACHINE VIBRATOR; JACKHAMMER; MASON TENDER MORTAR MIXER; PAVEMENT BREAKER; HANDLERS OF ALL STEEL MESH; SMALL GENERATORS FOR LABORERS' TOOLS; INSTALLATION OF BRIDGE DRAINAGE PIPE; PIPELAYERS; VIBRATOR TYPE ROLLERS; TAMPER; DRILL DOCTOR; TAIL OR SCREW OPERATOR ON ASPHALT PAVER; WATER PUMP (2"" AND SINGLE DIAPHRAM); NOZZLE (ASPHALT, GUNNITE, SEEDING AND SANDBLASTING); LABORERS ON CHAIN LINK FENCE ERECTION; ROCK SPLITTER AND POWER UNIT; PUSHER TYPE CONCRETE SAW AND ALL OTHER GAS, ELECTRIC, OIL AND AIR TOOL OPERATORS; WRECKING LABORERS; LASER MAN (ERIE COUNTY HEAVY & HIGHWAY) FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK | LABO0210-003 | $34.86 | $28.65 |
| LABORER GROUP 3 ALL ROCK OR DRILLING MACHINE OPERATORS (EXCEPT QUARRY MASTER AND SIMILAR TYPE); ACETYLENE TORCH OPERATOR; ASPHALT RAKER; POWDERMAN; WELDER (ERIE COUNTY HEAVY & HIGHWAY) FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK | LABO0210-003 | $35.06 | $28.65 |
| LABORER GROUP 4 BLASTERS; CURB & FLAT WORK FORM SETTERS (EXCEPT ON STRUCTURES); STONE OR GRANITE CURB SETTERS (ERIE COUNTY HEAVY & HIGHWAY) FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK | LABO0210-003 | $35.26 | $28.65 |
| LABORER GROUP 1: GENERAL; FLAGMAN; TOP MAN; WRECKERS (ERIE COUNTY SEWER/WATER) | LABO0210-003 | $34.66 | $28.65 |
| LABORER GROUP 1: MOLE NIPPER; POWDER HANDLER; TOP LABORER (ERIE COUNTY TUNNEL) FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK | LABO0210-003 | $36.16 | $28.65 |
| LABORER GROUP 2: AIR SPADE; JACKHAMMER; PAVEMENT BREAKER (ERIE COUNTY TUNNEL) FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK | LABO0210-003 | $36.31 | $28.65 |
| LABORER GROUP 2: FOUNDATION; ROD CARRIERS; PLASTER TENDER; SCAFFOLD BOOTMAN; PNEUMATIC, GAS, ELECTRIC TOOL OPERATOR; JACKHAMMER; CHIPPING GUNS (ERIE COUNTY SEWER/WATER) | LABO0210-003 | $34.76 | $28.65 |
| LABORER GROUP 3: MORTAR MIXER OVER 8 FEET IN DEPTH (ERIE COUNTY SEWER/WATER) | LABO0210-003 | $34.81 | $28.65 |
| LABORER GROUP 3: TOP BELL (ERIE COUNTY TUNNEL) FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK | LABO0210-003 | $36.41 | $28.65 |
| LABORER GROUP 4: PAVEMENT FORMSETTER; STEELBURNER; CAISSON; WAGON DRILL OPERATOR; PIPELAYER; SWING SCAFFOLD (ERIE COUNTY SEWER/WATER) | LABO0210-003 | $34.91 | $28.65 |
| LABORER GROUP 4: BOTTOM BELL; SIDE OR ROOFBELT DRILLER; BURNERS; TRACKMEN; NIPPERS; DERAILMEN; HOSEMEN; GROUTMEN; GRAVELMEN; FORM WORKERS; MOVERS & SHAFTMEN; CONVEYORMEN (ERIE COUNTY TUNNEL) FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK | LABO0210-003 | $36.91 | $28.65 |
| LABORER GROUP 5: UTILITY PAVE DRIVER; LASER OPERATOR (ERIE COUNTY SEWER/WATER) | LABO0210-003 | $35.26 | $28.65 |
| LABORER GROUP 5: POWDER MONKEY (ERIE COUNTY TUNNEL) FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK | LABO0210-003 | $37.01 | $28.65 |
| LABORER GROUP 6: BLASTER (ERIE COUNTY SEWER/WATER) | LABO0210-003 | $35.66 | $28.65 |
| LABORER GROUP 6: BLASTERS; IRONMEN; WELDER; HEADING DRILLER (ERIE COUNTY TUNNEL FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK | LABO0210-003 | $37.41 | $28.65 |
| LABORER GROUP 7: PILEDRIVER; RIGGER (ERIE COUNTY TUNNEL) FOR HEAVY/HIGHWAY & TUNNEL: ADDITIONAL $1.00 ADDED TO BASE RATE FOR ALL DELEADER & ASBESTOS WORK. ADDITIONAL $2.00 ADDED TO BASE RATE FOR ALL HAZARDOUS WASTE WORK. | LABO0210-003 | $37.66 | $28.65 |
| LABORERS: HEAVY AND HIGHWAY (ZONE I) GROUP 1 | LABO0621-001 | $33.93 | $28.69 |
| LABORERS: HEAVY AND HIGHWAY (ZONE I) GROUP 2 | LABO0621-001 | $34.33 | $28.69 |
| LABORERS: HEAVY AND HIGHWAY GROUP 2: BLASTERS, FORM SETTERS, STONE OR GRANITE CURB SETTERS; DESIGNATED ASPHALT RAKERS (NOT TO INCLUDE COLD PATCH), TAIL OR SCREW OPERATOR ON ASPHALT PAVER. ALL ROCK OR DRILLING MACHINE OPERATORS (EXCEPT QUARRY MASTER AND SIMILAR TYPE), ACETYLENE TORCH OPERATORS, POWDERMAN. (CATTARAUGUS COUNTY AND CHAUTAUQUA COUNTY (REMAINING TOWNSHIPS)) | LABO0621-002 | $34.33 | $28.69 |
| LABORERS: HEAVY AND HIGHWAYGROUP 1: FLAGMAN, OUTBOARD AND HAND BOATS, BULL FLOAT, CHAIN SAW, CONCRETE AGGREGATE BIN, CONCRETE BOOT, GIN BUGGY, HAND OR MACHINE VIBRATOR JACK HAMMER, MASON TENDER, MORTAR MIXER, PAVEMENT BREAKER, HANDLER OF ALL STEEL MESH, SMALL GENERATOR FOR LABORERS' TOOLS, INSTALLATION OF BRIDGE DRAINAGE PIPE; PIPE LAYERS, VIBRATOR TYPE ROLLERS, TAMPER DRILL DOCTOR, WATER PUMP OPERATOR (1 1/2"" AND SINGLE DIAPHRAGM), NOZZLE (ASPHALT, GUNITE, SEEDING AND SANDBLASTING) LABORERS ON CHAIN LINK FENCE ERECTION, ROCK SPLITTER AND POWER UNIT, PUSHER TYPE CONCRETE SAW AND ALL OTHER GAS, ELECTRIC, OIL AND AIR TOOL OPERATORS, WRECKING LABORERS. (CATTARAUGUS COUNTY AND CHAUTAUQUA COUNTY (REMAINING TOWNSHIPS)) | LABO0621-002 | $33.93 | $28.69 |
| PAINTERS: CATTARAUGUS, CHAUTAUQUA & ERIE COUNTIES | PAIN0004-001 | $38.50 | $28.40 |
| PAINTERS:, BUILDING CONSTRUCTION: BRUSH AND ROLLER (ERIE COUNTY) | PAIN0004-001 | $33.00 | $28.21 |
| PAINTERS:, BUILDING CONSTRUCTION: DRYWALL/TAPING (ERIE COUNTY) | PAIN0004-001 | $34.00 | $28.51 |
| PAINTERS:, BUILDING CONSTRUCTION: WALLCOVERING (ERIE COUNTY) | PAIN0004-001 | $33.00 | $28.21 |
| PAINTERS: BRIDGE PAINTER (HEAVY & HIGHWAY CONSTRUCTION) | PAIN0004-004 | $42.06 | $30.59 |
| GLAZIER | PAIN0004-007 | $34.68 | $27.64 |
| PAINTERS: BRIDGES (CATTARAUGUS COUNTY - Townships of Leon, Conewango, Randolph, South Valley, Napoli and New Albion; CHAUTAUQUA COUNTY - Townships of French Creek, Mina, Ripley, Westfield, Sherman, Clymer, Chautauqua, North Harmony, Harmony, Busti, Ellery, Stockton, Charlotte, Gerry, Ellicott, Jamestown, Kiantone, Carroll, Poland, Ellington and Cherry Creek.) | PAIN0004-008 | $42.06 | $30.59 |
| PAINTERS: BRIDGES (CATTARAUGUS COUNTY (Townships of Cold Spring, Elko, Mansfield, Little Valley, Salamanca Indian Reservation, Red House, Ellicottville, Great Valley, Carrolton, Franklinville, Humphrey, Allegany, Freedom, Farmersville, Lyndon, Ishua, Hinsdale, Olean and Portville)) | PAIN0004-017 | $42.06 | $30.59 |
| PLASTERER | PLAS0009-001 | $33.05 | $25.09 |
| CEMENT FINISHER | PLAS0111-001 | $33.65 | $31.47 |
| PLUMBER/PIPEFITTER: (ZONE 1) | PLUM0022-001 | $42.20 | $29.80 |
| STEAMFITTER: (ZONE 1) | PLUM0022-001 | $42.20 | $29.80 |
| PLUMBER/PIPEFITTER: (ZONE 2) | PLUM0022-004 | $42.20 | $29.80 |
| ROOFERS: COMPOSITION (ERIE COUNTY) | ROOF0074-001 | $34.96 | $26.03 |
| ROOFERS: SLATE & TILE (ERIE COUNTY) | ROOF0074-001 | $35.11 | $26.03 |
| ROOFER | ROOF0210-005 | $23.65 | $11.99 |
| SPRINKLER FITTER | SFNY0669-001 | $47.85 | $28.94 |
| SHEET METAL WORKER (ERIE COUNTY) | SHEE0071-001 | $39.50 | $29.18 |
| SHEET METAL WORKER (CATTARAUGUS AND CHAUTAUQUA COUNTIES:) | SHEE0112-001 | $31.00 | $24.56 |
| TRUCK DRIVERS: GROUP 1 PICKUPS, PANEL TRUCKS, FLATBOY MATERIAL TRUCKS (STRAIGHT JOBS), SINGLE-AXLE DUMP TRUCKS, DUMPSTERS, TANDEMS, BATCH TRUCKS, MECHANICS SEMI TRAILERS, LOW-BOY TRUCKS, ASPHALT DISTRIBUTOR TRUCKS, AGITATOR, MIXER TRUCKS AND DUMPCRETE TYPE VEHICLES, TRUCK MECHANICS, FUEL TRUCKS. (CATTARAUGUS AND CHAUTAUQUA COUNTIES) FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY. TRUCK DRIVER CLASSIFICATIONS | TEAM0264-001 | $49.66 | $16.82 |
| TRUCK DRIVERS: GROUP 2 SPECIALIZED EARTH MOVING EQUIPMENT-EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED, STRADDLE (ROSS) CARRIER, SELF-CONTAINED CONCRETE UNIT, OFF-HIGHWAY TANDEM BACK-DUMP, TWIN ENGINE EQUIPENT AND DOUBLE-HITCHED EQUIPMENT WHERE NOT SELF-LOADED. (CATTARAUGUS AND CHAUTAUQUA COUNTIES) FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY. TRUCK DRIVER CLASSIFICATIONS | TEAM0264-001 | $49.66 | $16.82 |
| TRUCK DRIVERS: INCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS WORK ON A HAZARDOUS WASTE SITE THEN ADDITIONAL $2.00 PER HOUR. FOOTNOTE: A. PENSION $56.20 PER DAY B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND AFTER THE HOLIDAY | TEAM0449-002 | $49.23 | $8.75 |
| TRUCK DRIVERS:: DUMP TRUCK ONLY, EXCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND AFTER THE HOLIDAY | TEAM0449-005 | $32.00 | $0.00 |
Other determinations for these counties
Change history
Changes WagePilot has seen on SAM.gov since it began mirroring this determination.
- First seen, Modification 3.
Upload one week of payroll. The NY20260008 rates are already loaded.
About these ratesWagePilot mirrors Davis-Bacon general wage determinations from SAM.gov, the official source, and re-checks each one daily. The wage determination incorporated in your contract governs, including its modification number, footnotes and any conformed classifications. WagePilot reviews payroll; it does not file, certify or give legal advice.